President Director of PLN: Total 35,000 MW Project Progress Has Reached Up to 40 Percent

By : Hariyanto And Aldo Bella Putra | Thursday, March 08 2018 - 18:00 IWST

Menteri Jonan bersama Dirut PLN Sofyan Basir
Menteri Jonan bersama Dirut PLN Sofyan Basir

INDUSTRY.co.id - Jakarta - The Ministry of Energy and Mineral Resources (ESDM) is optimistic that the implementation of the 35,000 MW electricity project is still on target. Since it was launched in mid-2015, the total operational already reached 1,362 MW.

President Director of PT PLN Sofyan Basir revealed, the total progress of 35,000 MW project developments has reached 30% to 40%.

"If asked 35,000 MW has been completed in two years I must lie, but if you talk the progress the development, is according to plan that is 30 to 40 percent," said Sofyan in Jakarta, Tuesday (6/3/2018).

Sofyan detailed the estimated period of construction of the plant. For hydroelectric power (PLTA) takes 5-6 years, geothermal (PLTP) can be 5-6 years, power plant above 600 MW reaches 6 years, and below 600 MW and 300 MW takes 3 years.

"The faster it (gas) generators can be 8 months to 1 year," said Sofyan.

One proof of progress is the construction of Java 7 Power Plant, PLTU Java 9, PLTU Java 10 with a total capacity of 4,000 MW which was officially inaugurated President Jokowi on October 5, 2017. In addition, there is still PLTU Java I in Cilacap the solution already reached 37 percent.

In addition to the 35,000 MW program, the government is also completing the 7,000 MW project as a continuation of Fast Track Program (FTP) I, FTP II and Regular. As of January 2018, a total of 6,424 MW or 82% of which is operating, and only 1,407 MW or 18% are still in construction.

News Comment

Today's Industry

Dr Paul Gardner-Stephen, Senior Lecturer, College of Science and Engineering, Flinders University (Photo by ICT Days)

Kamis, 24 September 2020 - 15:15 WIB

NBN Co to Spend $3bn Upgrading Half of FTTN Network to Full Fibre

In particular, the original Fibre-To-The-Premises (FTTP) plan had several key advantages that this announcement is not able to solve.

Rena Chua, Bug Bounty Advisor at HackerOne (Photo by Linkedin)

Kamis, 24 September 2020 - 14:15 WIB

How COVID-19 Is Impacting Security

With this accelerated pace of digital transformation, CISOs had to quickly facilitate new needs — while ensuring the security of existing systems and newly-acquired collaboration tools.

Ilustration Asia-Pacific’s First and Largest Collaborative Robots Virtual Expo (Photo by Universal Robots)

Selasa, 22 September 2020 - 17:00 WIB

Universal Robots Hosts First Virtual Collaborative Robots Exhibition & Conference in Asia-Pacific

Gain actionable insights on flexible and cost-effective automation solutions addressing post-pandemic ROI and safety challenges for small & medium businesses.

Published BSIMM11, The Latest Version of The BSIMM (Photo by EEJournal)

Senin, 21 September 2020 - 18:30 WIB

Synopsys Publishes BSIMM11 Study Highlighting Fundamental Shifts in Software Security

BSIMM11 reflects the software security practices observed across 130 firms from multiple industry verticals including financial services, FinTech, independent software vendors, cloud, health…

New Cloud-Based Technology That Delivers Secure Remote Access (Photo by News Break)

Senin, 21 September 2020 - 17:15 WIB

Check Point Software Technologies Redefines Secure Remote Access for Enterprises

This technology will integrate with Check Point´s Infinity architecture, and become the easiest and most secure solution for enterprises need to enable employees´ secure remote access to any…