Director General of Oil and Gas: Lifting Semester I 802.000 BOPD
By : Ridwan And Aldo Bella Putra | Wednesday, August 09 2017 - 16:08 IWST
5166
INDUSTRY.co.id - Jakarta - Director General of Oil and Gas (Directorate General of Oil and Gas) Ministry of Energy and Mineral Resources (ESDM) Ego Syahrial said the achievement of lifting or oil ready to sell in the first half of 802,000 BOPD. .
"Target at the end of 2017 is 815.000 BOPD yes less a little longer can reach the target of 2017," Ego said when giving exposure in the Ministry of Energy and Mineral Resources, Jakarta, Tuesday (08/08/2017)
While the achievement of natural gas in the first half of 2017 is 1,131,000 BOPD with target at the end of 2017 is 1,150,000 BOPD.
Director General of Oil and Gas explains that the effort made to pursue the realization of lifting is to apply the latest technology and appropriate in production.
It also maximizes the efficiency of time in drilling implementation. Exploration activities will be accelerated and completion of field development projects.
Production facilities will continue to be maintained to improve reliability and minimize unplanned shutdown.
Then the licensing sector will also be more concerned and facilitated such as land acquisition, administrative permits and so forth.
The achievement of gas pipeline in the first half has also been built along 10,425 km, while the total target in 2017 is 12,597 km.
The additional gas network in the first half of 2017 is targeted to reach 59,809 SR by the end of 2017. The Jargas program, in addition to being financed from the state budget, the government also encourages the General Gas Business Enterprises to participate in developing the city gas network (with details of PGN: 1,700 SR and Pertamina: 2,000 SR). (Ant)